Logan County Board
November Zoning Meeting

[November 03, 2026]  The Zoning and Economic Development Committee of the larger Logan County Board met on Monday, November 2nd for their monthly meeting. This meeting was held in the first floor courtroom of the Logan County Courthouse. Five of the six committee members were present, including Chairman Gil Turner, Vice Chairman Kathy Schmidt, Hannah Fitzpatrick, Joseph Kuhlman, and Keenan Leesman. Bob Sanders was the only member not present.

The committee’s first action was to approve the minutes from two previous meetings, those being for a special meeting on September 17th and a regular meeting on October 5th. Both were approved.

With no items for old business on the agenda, Turner moved on to the first of two new business items. This item was the discussion of data center ordinance revisions. Turner began with a brief overview of what has happened in the last couple of months regarding this ordinance. On September 17th, the Zoning and Economic Development Committee met to discuss the ordinance and the nearly 20 amendments that were suggested to be made to it. After the amendments were discussed and voted on, it was sent to State’s Attorney Brad Hauge for review. Hauge stated that he and the board’s attorney agreed to all the items with the exception of the M1/M2 zoning item.

M1 and M2 zoned parcels are zoned industrial. At that previous meeting, Zoning Officer Al Green said that they wanted to encourage data centers, should any apply in Logan County, to build where the land is already zoned industrial. He did say that they would have to leave the ability for agriculturally zoned land to be rezoned to M1 or M2.

Fitzpatrick stated that Tazewell County passed an ordinance with M1 and M2 restrictions, and Green shared that McClean County did as well. Turner decided to read Hauge’s response. It stated that most of the areas that are currently zoned M1 or M2 are concentrated in Lincoln and are already in use. He said that it would be hard to justify requiring them to build in these areas rather than agriculturally zoned ones. Turner then said that Green will write what they currently have into a comprehensive ordinance, then send it back to Hauge for review again, then it will be sent to the Zoning Board of Appeals.

[to top of second column]

 

Next, Green spoke on some of the data center ordinances of counties around Logan, specifically Sangamon and McClean. He said that the ordinances in these counties are very short, with McClean’s being only a few lines long. Logan County’s proposed ordinance, however, is very “comprehensive and restrictive.” He continued, saying that this ordinance would require data center companies to do much of their research and impact reports as a part of their application process. This would make the application process more expensive, and so would weed out any of the companies that were not very serious about building here.

Green gave two other updates on solar farms companies that are going to be submitting applications soon. First, there is an application for a solar farm that would be 900 acres large. The second planned solar farm is much smaller, only 30 acres, and would be going in near EATON in Lincoln. The land the company wants to build on is currently zoned residential, but it is being farmed.

Public comments came last this meeting, and the only commenter was an outraged resident of Latham. She argued that data centers should only be built on land that is zoned industrial, arguing that they are industrial buildings. She then accused the board members of wanting to “punish Latham” and called them “evil people.” After her comment, the committee adjourned the meeting.

[Matt Boutcher]


 